Skip sidebar navigation

Public Works Projects

Public works projects safely preserve existing infrastructure, increase roadway capacity, improve mobility and enhance neighborhood livability. 

Construction projects 

SE 4th St. Sewer Pipe Upgrade

The City is upgrading the pipe on SE 4th St. between SE Spruce Ave and SE Hogan Rd. due to age and condition.

Work schedule

  • Oct.– Dec. 2024
  • Monday – Friday, 7 a.m. – 6 p.m.

What to expect

  • Construction equipment and noise.
  • No on street parking near construction area. No parking signs will be placed 72-hours before closure.
  • Access for local traffic only.

Contractor

Nutter Corp

Contact

Jeff Loftin, Project Manager, 503-618-2525.

 

Kirk Park Wellhouse and Pipeline

Project Description

Construction of a well pump house at Kirk Park. The well has already been drilled and this construction will turn it into a useable water source for both Rockwood Water PUD and the City of Gresham. A new pipeline will be constructed connecting to the Rockwood District Offices, where the water will be treated.

Project Impacts

The park will remain open, but a large portion will be closed for construction; Partial street closures; Construction equipment, noise, vibration, and dust

Location: Kirk Park, NE Hassalo St, NE 190th Pl, NE Halsey St.

Schedule: Fall 2023 to Spring 2025

Contractor: Rotschy Inc.

Learn more about water supply projects.

North Gresham Elementary Well Drilling

Crews are drilling a groundwater well near North Gresham Elementary school, 1001 SE 217th Avenue. 

This project is expanding Gresham's groundwater supply.

Johnson Creek Sewer Pipe Upgrades

Project description  

The City is replacing an overhead sewer crossing above Johnson Creek between SW Highland Dr. and Springwater Trail. The pipeline upgrade is designed to withstand a large earthquake.

Improvements will include: 

  • Replacing and increasing the depth of the piles at either end of the crossing. This will provide a strong base for the span.  
  • Replacing the existing pipe and enclosing it with steel casing. 
  • Upgrading the manholes at either end of the span.  
  • Securing the above ground manholes to prevent disconnection.  

Schedule

Oct. 2024 – March 2025.
Work hours: Monday – Friday, 7:00 am – 6 pm

Construction impacts

  • Construction traffic on SW Highland Dr. and SW Nancy Ct
  • Watch for possible trail detours during construction.
  • Construction equipment and noise.

Project documents

Contact 

For more information contact Rob Chapler at 503-618-3458.

Sidewalk Improvements

Schedule

  • Ongoing; work hours may vary, but generally from 7:00 am-6:00 pm.
  • Some sidewalk work is scheduled before paving begins this summer.

Project overview 

The City will upgrade sidewalk ramps at intersections throughout Gresham. Installing sloped curb ramps provide improved safety at pedestrian crossings. The new ramps allow people with disabilities to safely travel from the sidewalk to the street.

Project impacts

During all construction activity, there will be delays and on-street parking will be impacted. We try to limit disruptions as much as possible.   

  • Sidewalk closed.
  • Bike lane closed.
  • Construction equipment parked in your neighborhood.
  • Partial road closure; flaggers may be directing traffic.
  • Reduced on-street parking.
  • Noise and dust.

Contact

Department of Environmental Services, 503-618-2525

Traffic Safety Improvements

The City’s Transportation Division is planning safety improvements at high crash rate locations across the City, funded by ODOT's All Roads Transportation Safety (ARTS) Program. Work will include:

  • Installing a non-mountable curb on the yellow painted centerline approaching the intersection.
  • The non-mountable curb will restrict access to right in/out. Left turns will be prohibited.

Schedule

June-August 2024

Locations

  1. 181st and Halsey
  2. Hogan and Division
  3. Hogan and Stark
  4. Kane and Division

Project impact

  • While this project will not close any driveways, it does change how driveways can be used.
  • Work is expected to start early summer and will take approximately one week to complete each curb, weather permitted.

For more information contact Lesley Nebeker at 503-618-2472

Water Transmission Upgrades: Multiple Locations

The City is increasing water pipe capacity. Crews are upgrading water mains and connecting service lines with new water treatment and water storage facilities. This project includes replacing 1200 linear feet of water distribution lines in residential areas. 

Schedule

Last spring crews installed new underground water mains. Paving is scheduled for  late-September. Weather may impact paving schedule.

Location or work

NE 197th Ave (Glisan St. to Davis St.)

Work hours
Mon-Fri, 7am-6pm

Project impacts

• Limited to no street parking.
• Lane closure or full street closure.
• Limited driveway access.
• Detour to bus route (TriMet). Check TriMet.

Contact

Jason Branstetter, Project Manager, 503-618-2516

Salquist Waterline Improvement

The City is replacing part of a waterline on SE Salquist Road between SE Eagle Avenue to SE Night Heron Place.

Work hours

  • October - December 
  • Monday - Friday, 7:00 am - 6:00 pm

What to expect

• Construction equipment, noise, vibration, gravel and dust.
• Limited to no street parking.
• Lane closures, contractor will provide 24-48 hour notice prior to closure.
• Limited water shutoff, contractor will give 24-48 hour notice prior to shut off.

Contact

Abe Eddy, Project Manager, 503-618-2525.

Contractor

KKLA Contractors